Costs
The Costs tab rolls up the money side of a run: what each activity, resource, and entity cost, and where the cost went.

What it shows
Section titled “What it shows”- Activity cost: the processing and per-entity cost at each activity, and how many entities it handled.
- Resource cost: for each resource, the cost of time in use, idle, on break, in downtime, and overtime, and its total.
- Entity cost: the total cost each entity type accumulated, split into waiting and working.
A donut and a bar chart summarize where the cost is concentrated, so the most expensive parts of the process stand out. For costs to appear, first set costs on your activities, resources, and entities (see Resource Cost).